The West Loveland Avenue Bridge is scheduled to be repaired in 2024. The bridge is owned and maintained by both Clermont and Hamilton County, and the project is being largely funded by Hamilton County, state grant funding, and an allocation from the Clermont County Commissioners. The city is contributing funds toward decorative railing and new lighting.
In 2021, the City of Loveland and Hamilton County submitted a joint grant application to replace the north sidewalk, as well the railings, walls and bridge abutments. However, private utility relocation for conduit located within the sidewalks delayed the project. In July 2022, the north side of the bridge's sidewalk was paved with asphalt for pedestrian safety. The bridge is expected to remain open to traffic with a reduced number of lanes during the repairs.
Project Dates
Start Date: January 2024
Estimated Completion: September 2024
Contact
The bidding and contract for the project is being managed by Hamilton County. For questions, please contact (513) 946-4250.