The West Loveland Avenue Bridge is scheduled to be repaired in 2024. During construction, the bridge will remain open to traffic with a reduced number of lanes.
The bridge is owned and maintained by both Clermont and Hamilton County. The project is funded by Hamilton County, state grant funding, and an allocation from the Clermont County Commissioners. The City of Loveland is contributing funds toward decorative railings and new lighting.
In 2021, the City of Loveland and Hamilton County submitted a joint grant application to replace the north sidewalk, as well the railings, walls and bridge abutments. However, private utility relocation for conduit located within the sidewalks delayed the project. In July 2022, the north side of the bridge's sidewalk was paved with asphalt for pedestrian safety.
Project Dates
Start Date: March 25, 2024
Estimated Completion: Aug. 30, 2024
Contact
The project is being managed by the Hamilton County Engineer's Office. For questions, please contact (513) 946-4250.