Repairing East Loveland Avenue is a collaborative project between the City of Loveland, Clermont County, and the Metropolitan Sewer District (MSD). There are many parts of this large project:
- Clermont County is providing $478,320 for the replacement of the bridge on East Loveland Avenue over Bares Run near #250 E. Loveland Ave.
- MSD will replace and upsize about 1,300 LF of the sanitary sewer from #220 to #362 E. Loveland Ave. MSD is paying a total of approximately $686,200 for the sanitary sewer work.
- The city is receiving $722,400 of state grant funding to install sidewalks on both sides of the road between #227 to #356, relocate water main around the future bridge wingwalls, make storm sewer system improvements, and repave a portion of the roadway while the bridge replacement project is being performed.
Project Dates
Start Date: Road closure begins Jan. 30, 2024
Estimated Date for Road to Reopen: July 2024
Estimated Project Completion: Late Summer 2024
Closures & Detour
The bridge replacement and sunderground utility work will require a full roadway closure and detour route. The full road closure began Jan. 30, 2024. Tentatively, crews hope to reopen one lane of traffic July 15, 2024, to send the detour.
Contact
For questions, please contact the City Manager at (513) 707-1454.