State Route 48 Sewer Main Extension

Location: State Route 48 & Butterworth Road                                                               

Project Boundaries

Contractor: Larry Smith, Inc.                                                             

City Contact: Cindy Klopfenstein, City Engineer (513) 707-6114

Project Cost: $457,175                                                       

Sign Up For Project Alerts: Click Here

Project Scope:

The project consists of installing 1,455 L.F. of 12" diameter sanitary sewer along SR 48 from approximately Kipp Ln. to Butterworth Rd. and along Butterworth Rd. from SR 48 to the future Chimneyridge subdivision tie-in to the south of Brandywine Lane. The sanitary sewer construction contract was awarded to Larry Smith, Inc. for $457,175.00.  Work is scheduled to begin on June 1, 2021.  The work zone will be limited to a one lane closure with temporary traffic signals provided to maintain 2-way traffic. Expect traffic delays.  The contract final completion date is September 30, 2021.